Cambodian aid project partly funded by Australia led to child deaths, report finds
Sydney Morning Herald | 9 Feb. 2014
Looking for water: Hut Heap, 13, and her brother Hut Hoeub, 9, drowned in a pond in the Battambang resettlement camp.
A project partly funded by Australia to rebuild Cambodia’s
dilapidated railway was deeply flawed, caused harm to thousands of
impoverished people and contributed to the deaths of several children,
an internal review has found.
A scathing review found the family and 50 others taken to a
resettlement site were not provided with potable water, violating
compliance of the Asian Development Bank’s rules on resettling people.
“Any reasonable person would conclude that the resettled
people, including the children concerned, would resort to other sources
of water in this situation,” a report by the bank’s Compliance Review
Panel found. “It was foreseeable that an accident of this nature could
happen,” it said.
Advertisement
Fairfax Media reported in November 2010 that the children
went to the eight-metre pond because there was no fresh piped water at
the resettlement site in Battambang province. When Hut Hoeub fell in
his sister tried to save him but they both drowned.
The 180-page report said the $US140 million ($156 million)
project caused “direct, adverse and material harm” to thousands of
evicted families.
The project is operated by Toll Royal Railway, a subsidiary
of Melbourne firm Toll Holdings and its partner, Cambodia’s Royal Group
of Companies, and financed by the Asian Development Bank and the former
Australian development agency AusAid.
The report said another resettled child was killed when hit
by a vehicle while walking a longer than usual distance home from
school.
An estimated 4000 families, most of them impoverished, were
forced from their homes to make way for the strategically important
railway that will link Singapore and China through Thailand, Malaysia
and Vietnam.
The report, released after a 17-month investigation, said
there were major flaws when the Asian Development Bank designed the
project in 2006. The report identified inadequate consultation with
affected families, a lack of indexed compensation for them and
replacement houses that were of such a poor standard that they did not
improve the situation of the resettled families.
Formed in the 1960s to facilitate economic growth in Asia’s
developing countries with the aim of alleviating poverty, the project
in Cambodia actually drove families deeper into debt and poverty, the
report said.
Resettlement sites were far from families’ jobs and there
were “consideration inaccuracies” in inventories for the properties that
families were forced to leave. Some families were given only $US200 to
relocate.
The report said families should be given up to $US4 million
in additional compensation. It said the bank’s staff must “undergo a
mind shift” in their approach to future resettlement projects.
Mistakes were “particularly grievous” because they repeated
many of the same mistakes made on a past road building project
undertaken by the bank, the report said.
Human rights groups and non-government organisations have been campaigning for the bank and AusAid to do more for the families.
“It is an outrage that the ADB failed to act all these years
while people fell into a spiral of debt and poverty after the
resettlement plans it approved turned out to be disastrous,” said David
Pred, managing director of the NGO Inclusive Development International,
one of the campaigners.
In October 2012, 30 of the affected families filed a
complaint with the Australian Human Rights Commission over what they
said were breaches of basic human rights.
Following the report’s release the bank has promised to
consult those involved in the project, including families, before
working out a plan of action within two months.
AusAid, the agency responsible at the time for managing
Australia’s overseas aid program, rejected criticisms of the project in
2012, saying it was “fully consistent with Australia’s international
legal obligations”.
AusAid had provided $US23.5 million for the project in two tranches.
The agency was integrated into the Department of Foreign
Affairs and Trade last year. A spokesman for the department said the
Australian government supported the decision of the bank to bring the
project into full compliance with its safeguard policies, as recommended
by the review panel.
“Although Australia no longer finances works on the railway,
we look forward to working constructively with partners responsible for
implementation of the report’s recommendations,” the spokesman said.
Comment was being sought from Toll Royal Railway, which has a 30-year contract to build and run the railway.